South Dakota logo   Tent in campground Fisherman with trout in hand Big Game hunter Deer Pheasant walleye swimming
   Home FAQ's Site Index Contact Us Our Privacy Policy Disclaimer

Game Fish and Parks logo

--

About GFP

GFP Commission
GFP NEWS
Administration
Wildlife

Parks & Recreation
Licensing & Reservations
Online Shopping
Outdoor Education
Outdoor Recreation
Publications
Employment & Internships
Volunteering
Parks & Wildlife Foundation
GFP Calendar
-




Game Fish and Parks logo

 

"));

LEGION LAKE CAMPGROUND

ROAD CONSTRUCTION & UTILITY RELOCATION

CUSTER COUNTY, SOUTH DAKOTA

PROJECT NO. Legn0OCa

BID OPENING - SEPTEMBER 15, 2009

Item Item Description Estimated Units Simon Contractors of SD, Inc. Site Work Specialists, Inc. R.C.S. Construction, Inc. Quinn Construction, Inc. Hills Materials Company MainLine Contracting, Inc.
No. Quantity
  Bid Tabulation Results     Unit Price Total Unit Price Total Unit Price Total Unit Price Total Unit Price Total Unit Price Total
1 Mobilization 1 LS  $   15,000.00  $         15,000.00  $     3,800.00  $      3,800.00  $   17,973.30  $     17,973.30  $   25,000.00  $     25,000.00  $   10,000.00  $     10,000.00  $   25,000.00  $     25,000.00
2 Incidental Work 1 LS  $     3,000.00  $           3,000.00  $     9,250.00  $      9,250.00  $   10,309.01  $     10,309.01  $   11,000.00  $     11,000.00  $   20,000.00  $     20,000.00  $   24,200.00  $     24,200.00
3 Traffic Control 1 LS  $       800.00  $              800.00  $     1,750.00  $      1,750.00  $     1,125.44  $      1,125.44  $     1,000.00  $      1,000.00  $     1,250.00  $      1,250.00  $     1,200.00  $      1,200.00
4 Clearing/Tree Removals 1 LS  $     1,800.00  $           1,800.00  $     1,700.00  $      1,700.00  $     1,629.41  $      1,629.41  $     2,500.00  $      2,500.00  $     1,100.00  $      1,100.00  $     2,000.00  $      2,000.00
5 Tree Removal (over 8" DBH) 2 EA  $       500.00  $           1,000.00  $       750.00  $      1,500.00  $       458.22  $         916.44  $     1,000.00  $      2,000.00  $       350.00  $         700.00  $       250.00  $         500.00
6 Asphalt Removal (Trench Work) 20 SY  $         20.00  $              400.00  $         40.00  $         800.00  $           2.11  $           42.20  $           5.00  $         100.00  $           7.00  $         140.00  $           5.00  $         100.00
7 Remove 24" CMP 50 LF  $           5.00  $              250.00  $         16.00  $         800.00  $         10.12  $         506.00  $           5.00  $         250.00  $         14.00  $         700.00  $           8.00  $         400.00
8 In-Place Asphalt and Base Course Reclamation 3,250 SY  $           2.80  $           9,100.00  $           3.70  $     12,025.00  $           2.19  $      7,117.50  $           2.50  $      8,125.00  $           3.00  $      9,750.00  $           4.00  $     13,000.00
9 Place Salvaged Millings/Base Course 1,450 TON  $           4.60  $           6,670.00  $           3.00  $      4,350.00  $           5.48  $      7,946.00  $           7.00  $     10,150.00  $         13.00  $     18,850.00  $           8.00  $     11,600.00
10 Borrow Material (Haul and Place) 500 CY  $         14.00  $           7,000.00  $         10.00  $      5,000.00  $         10.74  $      5,370.00  $         10.00  $      5,000.00  $         24.00  $     12,000.00  $         23.00  $     11,500.00
11 Unclassified Excavation (including topsoil) 425 CY  $         19.00  $           8,075.00  $           5.00  $      2,125.00  $           6.77  $      2,877.25  $         14.00  $      5,950.00  $         24.00  $     10,200.00  $         12.00  $      5,100.00
12 Rock Excavation (Trench) 100 LF  $         20.00  $           2,000.00  $         35.00  $      3,500.00  $         28.13  $      2,813.00  $         29.00  $      2,900.00  $         13.00  $      1,300.00  $         10.00  $      1,000.00
13 Rock Excavation (Site) 80 CY  $         35.00  $           2,800.00  $         30.00  $      2,400.00  $         28.13  $      2,250.40  $         36.00  $      2,880.00  $         38.00  $      3,040.00  $         25.00  $      2,000.00
14 Remove Concrete 1,371 SF  $           1.10  $           1,508.10  $           6.00  $      8,226.00  $           1.69  $      2,316.99  $           0.50  $         685.50  $           0.50  $         685.50  $           1.00  $      1,371.00
15 6" Reinforced Concrete Pavement & Sidewalk 1,500 SF  $           9.00  $         13,500.00  $           8.00  $     12,000.00  $           8.19  $     12,285.00  $           8.25  $     12,375.00  $           6.50  $      9,750.00  $           8.00  $     12,000.00
16 Limestone Base Course  1,000 TON  $         27.00  $         27,000.00  $         19.50  $     19,500.00  $         22.89  $     22,890.00  $         34.00  $     34,000.00  $         35.00  $     35,000.00  $         25.00  $     25,000.00
17 Asphalt Concrete Pavement (Class E or G Type 1) 925 TON  $         84.00  $         77,700.00  $       104.00  $     96,200.00  $         99.72  $     92,241.00  $         95.00  $     87,875.00  $         93.50  $     86,487.50  $       106.00  $     98,050.00
18 Precast Concrete Parking Curb 2 EA  $         65.00  $              130.00  $         92.00  $         184.00  $       118.66  $         237.32  $       300.00  $         600.00  $         40.00  $           80.00  $         75.00  $         150.00
19 4" PVC Electrical Conduit Crossings (Furnish & Install) 170 LF  $         10.00  $           1,700.00  $         18.50  $      3,145.00  $           9.01  $      1,531.70  $           8.00  $      1,360.00  $         13.00  $      2,210.00  $         17.00  $      2,890.00
20 48" BHP Primary Utility Trench  950 LF  $           7.00  $           6,650.00  $         22.00  $     20,900.00  $         22.00  $     20,900.00  $         12.00  $     11,400.00  $         24.00  $     22,800.00  $         12.00  $     11,400.00
21 24" CMP 48 LF  $         50.00  $           2,400.00  $         43.50  $      2,088.00  $         37.33  $      1,791.84  $         40.00  $      1,920.00  $         75.00  $      3,600.00  $         35.00  $      1,680.00
22 24" CMP FES 2 EA  $       260.00  $              520.00  $       180.00  $         360.00  $       248.29  $         496.58  $       200.00  $         400.00  $       275.00  $         550.00  $       350.00  $         700.00
23 2" PE Water Main & Fittings 400 LF  $         18.00  $           7,200.00  $         21.00  $      8,400.00  $         17.31  $      6,924.00  $         25.00  $     10,000.00  $         30.00  $     12,000.00  $         31.00  $     12,400.00
24 Tracer Wire Access Box 2 EA  $         80.00  $              160.00  $         24.50  $           49.00  $       165.83  $         331.66  $       500.00  $      1,000.00  $         40.00  $           80.00  $         50.00  $         100.00
25 1" Curb Stop & Box (Stop & Waste) 2 EA  $       300.00  $              600.00  $       515.00  $      1,030.00  $       266.94  $         533.88  $       750.00  $      1,500.00  $       380.00  $         760.00  $       220.00  $         440.00
26 2" Curb Stop & Box (Stop & Waste) 2 EA  $       600.00  $           1,200.00  $       800.00  $      1,600.00  $       540.94  $      1,081.88  $     1,000.00  $      2,000.00  $       660.00  $      1,320.00  $       575.00  $      1,150.00
27 Yard Hydrant & Lead (Stop & Waste) 2 EA  $       800.00  $           1,600.00  $       560.00  $      1,120.00  $       782.41  $      1,564.82  $       600.00  $      1,200.00  $       975.00  $      1,950.00  $       600.00  $      1,200.00
28 Reconnect Comfort Station Water Service 1 EA  $       950.00  $              950.00  $     1,450.00  $      1,450.00  $       631.24  $         631.24  $     1,400.00  $      1,400.00  $     1,950.00  $      1,950.00  $       850.00  $         850.00
29 6" PVC Sewer Main 131 LF  $         22.00  $           2,882.00  $         21.00  $      2,751.00  $         15.22  $      1,993.82  $         30.00  $      3,930.00  $         29.00  $      3,799.00  $         26.00  $      3,406.00
30 4" PVC Sewer Main 217 LF  $         19.00  $           4,123.00  $         12.00  $      2,604.00  $         13.51  $      2,931.67  $         24.00  $      5,208.00  $         27.00  $      5,859.00  $         24.00  $      5,208.00
31 4" PVC Cleanouts 3 EA  $       260.00  $              780.00  $       190.00  $         570.00  $       220.77  $         662.31  $       650.00  $      1,950.00  $       350.00  $      1,050.00  $       200.00  $         600.00
32 Class B Riprap 10 TON  $         80.00  $              800.00  $         62.00  $         620.00  $         40.24  $         402.40  $         65.00  $         650.00  $         70.00  $         700.00  $         60.00  $         600.00
33 Erosion Control Blanket 175 SY  $           3.15  $              551.25  $           1.80  $         315.00  $           4.62  $         808.50  $           4.00  $         700.00  $           3.10  $         542.50  $           5.00  $         875.00
34 Wattles 1,250 LF  $           3.15  $           3,937.50  $           4.21  $      5,262.50  $           8.44  $     10,550.00  $           5.00  $      6,250.00  $           3.10  $      3,875.00  $           5.00  $      6,250.00
35 Seeding, Fertilizing, Mulching 10,950 SY  $           0.55  $           6,022.50  $           0.63
 $      6,898.50
 $           0.50  $      5,475.00  $           1.00  $     10,950.00  $           0.54  $      5,913.00  $           1.00  $     10,950.00
 Totals   
 $     219,809.35
  $244,273.00
  $249,457.56
  $274,208.50
  $289,991.50
  $294,870.00