Campground Electrical Pedestals
Oakwood Lake State Park & Pelican Lake Recreation Area
Brookings & Codington Counties, South Dakota
Project Nos. Oakw0OCb & PelS0WBb
BID OPENING - SEPTEMBER 17, 2009 AT 3:00 PM
| OAKWOOD LAKE |
BID QUANTITIES |
BIDDERS |
| Dells Electric Inc |
B&H Electric |
Brookings Electric |
Eide Electric |
| ITEM NO. |
ITEMS |
| Qty |
Units |
UNIT |
AMOUNT |
UNIT |
AMOUNT |
UNIT |
AMOUNT |
UNIT |
AMOUNT |
| 1 |
Mobilization |
1 |
LS |
$2,334.00 |
$2,334.00 |
$950.00 |
$950.00 |
$1,833.13 |
$1,833.13 |
$1,500.00 |
$1,500.00 |
| 2 |
Reconnect Existing Pedestals Pads 55 and 11 |
2 |
EA |
$85.00 |
$170.00 |
$50.00 |
$100.00 |
$80.00 |
$160.00 |
$100.00 |
$200.00 |
| 3 |
400 Amp. Panel, Service, Ground System, Panel Support for complete and operable system |
5 |
EA |
$2,200.00 |
$11,000.00 |
$1,266.00 |
$6,330.00 |
$1,819.12 |
$9,095.60 |
$2,080.00 |
$10,400.00 |
| 4 |
50 Amp Electrical Pedestals (2 extra) |
68 |
EA |
$230.00 |
$15,640.00 |
$1,266.00 |
$11,696.00 |
$179.30 |
$12,192.40 |
$204.00 |
$13,872.00 |
| 5 |
3-4/0 Alum USE with ground and trench |
10,200 |
LF |
$3.46 |
$35,292.00 |
$2.73 |
$27,846.00 |
$2.53 |
$25,806.00 |
$3.62 |
$36,924.00 |
| 6 |
Bollard Lighting with foundation |
6 |
EA |
$1,000.00 |
$6,000.00 |
$634.00 |
$3,804.00 |
$860.20 |
$5,161.20 |
$677.00 |
$4,062.00 |
| 7 |
Branch circuit conductor for lighting with trench |
450 |
LF |
$2.66 |
$1,197.00 |
$1.05 |
$472.50 |
$1.21 |
$544.50 |
$2.00 |
$900.00 |
| 8 |
Reconnect Cabins 1 & 2 to new panel “A” |
1 |
LS |
$2,200.00 |
$2,200.00 |
$100.00 |
$100.00 |
$170.04 |
$170.04 |
$100.00 |
$100.00 |
| 9 |
Road Bore under asphalt paving |
200 |
LF |
$4.50 |
$900.00 |
$17.50 |
$3,500.00 |
$13.70 |
$2,740.00 |
$5.00 |
$1,000.00 |
| TOTAL BID FOR OAKWOOD LAKES: |
$74,733.00 |
$54,798.50 |
$57,702.87 |
$68,958.00 |
| PELICAN LAKE |
BID QUANTITIES |
BIDDERS |
| Dells Electric |
B&H Electric |
Brookings Electric |
Eide Electric |
| ITEM NO. |
ITEMS |
| Qty |
Units |
UNIT |
AMOUNT |
UNIT |
AMOUNT |
UNIT |
AMOUNT |
UNIT |
AMOUNT |
| 1 |
Mobilization |
1 |
LS |
$2,334.00 |
$2,334.00 |
$950.00 |
$950.00 |
$1,976.59 |
$1,976.59 |
$1,800.00 |
$1,800.00 |
| 2 |
Install 50 amp pedestals to replace existing 30 amp pedestals
(one extra)
|
22 |
EA |
$198.00 |
$4,356.00 |
$172.00 |
$3,784.00 |
$180.82 |
$3,978.04 |
$204.00 |
$4,488.00 |
| 3 |
Install 3-4/0 USE with ground and trench |
2,100 |
LF |
$3.46 |
$7,266.00 |
$2.73 |
$5,733.00 |
$2.53 |
$5,313.00 |
$3.62 |
$7,602.00 |
| 4 |
400 Amp. Panel, Service, Ground System, Panel Support for
complete and operable system |
1 |
EA |
$2,200.00 |
$2,200.00 |
$1,266.00 |
$1,266.00 |
$2,338.92 |
$2,338.92 |
$2,080.00 |
$2,080.00 |
| 5 |
Reinstallation of existing panels and 3 new 150 amp breakers |
2 |
EA |
$300.00 |
$600.00 |
$1,000.00 |
$2,000.00 |
$776.51 |
$1,553.02 |
$100.00 |
$200.00 |
| 6 |
Road Bore no sleeve |
|
LF |
$4.50 |
|
|
|
$13.70 |
|
$5.00 |
|
| 7 |
Bollard Lighting with foundation |
1 |
EA |
$1,000.00 |
$1,000.00 |
$634.00 |
$634.00 |
$306.88 |
$306.88 |
$677.00 |
$677.00 |
| 8 |
Branch circuit conductor for lighting with trench |
150 |
LF |
$2.66 |
$399.00 |
$1.05 |
$157.50 |
$1.23 |
$184.50 |
$2.00 |
$300.00 |
| TOTAL BID FOR PELICAN LAKE: |
$18,155.00 |
$14,524.50 |
$15,650.95 |
$17,147.00 |
| TOTAL BID FOR OAKWOOD & PELICAN LAKE: |
$92,888.00 |
$69,323.00 |
$73,353.82 |
$86,105.00 |
| OAKWOOD LAKE |
BID QUANTITIES |
BIDDERS |
| Efraimson Electric |
Engelstad Electric |
Miller Electric |
Arneson Electric |
| ITEM NO. |
ITEMS |
| Qty |
Units |
UNIT |
AMOUNT |
UNIT |
AMOUNT |
UNIT |
AMOUNT |
UNIT |
AMOUNT |
| 1 |
Mobilization |
1 |
LS |
$1,650.00 |
$1,650.00 |
$5,000.00 |
$5,000.00 |
$2,614.00 |
$2,614.00 |
$1,258.00 |
$1,258.00 |
| 2 |
Reconnect Existing Pedestals Pads 55 and 11 |
2 |
EA |
$75.00 |
$150.00 |
$60.00 |
$120.00 |
$97.00 |
$194.00 |
$40.00 |
$80.00 |
| 3 |
400 Amp. Panel, Service, Ground System, Panel Support for complete and operable system |
5 |
EA |
$2,500.00 |
$12,500.00 |
$2,600.00 |
$13,000.00 |
$2,261.00 |
$11,305.00 |
$2,016.00 |
$10,080.00 |
| 4 |
50 Amp Electrical Pedestals (2 extra) |
68 |
EA |
$245.00 |
$16,660.00 |
$275.00 |
$18,700.00 |
$310.00 |
$21,080.00 |
$264.00 |
$17,952.00 |
| 5 |
3-4/0 Alum USE with ground and trench |
10,200 |
LF |
$3.25 |
$33,150.00 |
$2.75 |
$28,050.00 |
$2.70 |
$27,540.00 |
$3.47 |
$35,394.00 |
| 6 |
Bollard Lighting with foundation |
6 |
EA |
$1,000.00 |
$6,000.00 |
$815.00 |
$4,890.00 |
$342.00 |
$2,052.00 |
$894.00 |
$5,364.00 |
| 7 |
Branch circuit conductor for lighting with trench |
450 |
LF |
$3.00 |
$1,350.00 |
$1.00 |
$450.00 |
$1.88 |
$846.00 |
$1.38 |
$621.00 |
| 8 |
Reconnect Cabins 1 & 2 to new panel “A” |
1 |
LS |
$250.00 |
$250.00 |
$300.00 |
$300.00 |
$370.00 |
$370.00 |
$120.00 |
$120.00 |
| 9 |
Road Bore under asphalt paving |
200 |
LF |
$10.00 |
$2,000.00 |
$4.00 |
$800.00 |
$9.75 |
$1,950.00 |
$5.00 |
$1,000.00 |
| TOTAL BID FOR OAKWOOD LAKES: |
$73,710.00 |
$71,310.00 |
$67,951.00 |
$71,869.00 |
| PELICAN LAKE |
BID QUANTITIES |
BIDDERS |
| Efraimson Electric |
Engelstad Electric |
Miller Electric |
Arneson Electric |
| ITEM NO. |
ITEMS |
| Qty |
Units |
UNIT |
AMOUNT |
UNIT |
AMOUNT |
UNIT |
AMOUNT |
UNIT |
AMOUNT |
| 1 |
Mobilization |
1 |
LS |
$500.00 |
$500.00 |
$1,200.00 |
$1,200.00 |
$904.00 |
$904.00 |
$500.00 |
$500.00 |
| 2 |
Install 50 amp pedestals to replace existing 30 amp pedestals
(one extra)
|
22 |
EA |
$260.00 |
$5,720.00 |
$275.00 |
$6,050.00 |
$310.00 |
$6,820.00 |
$264.00 |
$5,808.00 |
| 3 |
Install 3-4/0 USE with ground and trench |
2,100 |
LF |
$3.45 |
$7,245.00 |
$2.75 |
$5,775.00 |
$2.70 |
$5,670.00 |
$3.47 |
$7,287.00 |
| 4 |
400 Amp. Panel, Service, Ground System, Panel Support for
complete and operable system |
1 |
EA |
$3,100.00 |
$3,100.00 |
$2,340.00 |
$2,340.00 |
$2,019.00 |
$2,019.00 |
$2,016.00 |
$2,016.00 |
| 5 |
Reinstallation of existing panels and 3 new 150 amp breakers |
2 |
EA |
$500.00 |
$1,000.00 |
$1,000.00 |
$2,000.00 |
$693.00 |
$1,386.00 |
$2,016.00 |
$4,032.00 |
| 6 |
Road Bore no sleeve |
|
LF |
$10.00 |
|
$4.00 |
|
$9.75 |
|
$5.00 |
|
| 7 |
Bollard Lighting with foundation |
1 |
EA |
$1,000.00 |
$1,000.00 |
$815.00 |
$815.00 |
$342.00 |
$342.00 |
$894.00 |
$894.00 |
| 8 |
Branch circuit conductor for lighting with trench |
150 |
LF |
$3.00 |
$450.00 |
$1.00 |
$150.00 |
$1.88 |
$282.00 |
$1.38 |
$207.00 |
| TOTAL BID FOR PELICAN LAKE: |
$19,015.00 |
$18,330.00 |
$17,423.00 |
$20,744.00 |
| TOTAL BID FOR OAKWOOD & PELICAN LAKE: |
$92,725.00 |
$89,640.00 |
$85,374.00 |
$92,613.00 |
| OAKWOOD LAKE |
BID QUANTITIES |
BIDDERS |
| Ferding Electric |
|
|
|
| ITEM NO. |
ITEMS |
| Qty |
Units |
UNIT |
AMOUNT |
UNIT |
AMOUNT |
UNIT |
AMOUNT |
UNIT |
AMOUNT |
| 1 |
Mobilization |
1 |
LS |
$1,500.00 |
$1,500.00 |
|
| 2 |
Reconnect Existing Pedestals Pads 55 and 11 |
2 |
EA |
$60.00 |
$120.00 |
| 3 |
400 Amp. Panel, Service, Ground System, Panel Support for complete and operable system |
5 |
EA |
$2,070.00 |
$10,350.00 |
| 4 |
50 Amp Electrical Pedestals (2 extra) |
68 |
EA |
$211.00 |
$14,348.00 |
| 5 |
3-4/0 Alum USE with ground and trench |
10,200 |
LF |
$4.00 |
$40,800.00 |
| 6 |
Bollard Lighting with foundation |
6 |
EA |
$815.00 |
$4,890.00 |
| 7 |
Branch circuit conductor for lighting with trench |
450 |
LF |
$2.00 |
$900.00 |
| 8 |
Reconnect Cabins 1 & 2 to new panel “A” |
1 |
LS |
$110.00 |
$110.00 |
| 9 |
Road Bore under asphalt paving |
200 |
LF |
$14.50 |
$2,900.00 |
| TOTAL BID FOR OAKWOOD LAKES: |
$75,918.00 |
| PELICAN LAKE |
BID QUANTITIES |
BIDDERS |
| Ferding Electric |
|
| ITEM NO. |
ITEMS |
| Qty |
Units |
UNIT |
AMOUNT |
| 1 |
Mobilization |
1 |
LS |
$1,500.00 |
$1,500.00 |
| 2 |
Install 50 amp pedestals to replace existing 30 amp pedestals
(one extra)
|
22 |
EA |
$217.00 |
$4,774.00 |
| 3 |
Install 3-4/0 USE with ground and trench |
2,100 |
LF |
$4.00 |
$8,400.00 |
| 4 |
400 Amp. Panel, Service, Ground System, Panel Support for
complete and operable system |
1 |
EA |
$2,170.00 |
$2,170.00 |
| 5 |
Reinstallation of existing panels and 3 new 150 amp breakers |
2 |
EA |
$2,100.00 |
$4,200.00 |
| 6 |
Road Bore no sleeve |
|
LF |
$14.50 |
|
| 7 |
Bollard Lighting with foundation |
1 |
EA |
$815.00 |
$815.00 |
| 8 |
Branch circuit conductor for lighting with trench |
150 |
LF |
$2.00 |
$300.00 |
| TOTAL BID FOR PELICAN LAKE: |
$22,159.00 |
|
| TOTAL BID FOR OAKWOOD & PELICAN LAKE: |
$98,077.00 |
|