| SOUTH DAKOTA DEPARTMENT OF GAME, FISH PARKS |
| NO. OF PROPOSALS OUT: |
23 |
SUMMARY OF BIDS ON: |
Shoreline Stabilization Project |
Project # WPol0PMa |
| NO. OF BIDS RECEIVED: |
11 |
West Pollock Recreation Area |
|
| DATE: |
October 22, 2009 |
Campbell County, South Dakota |
Page 1 of 1 |
|
| |
BID QUANTITIES |
BIDDERS |
| AGE Corporation |
Kenzy Construction |
Steve Lehrkamp Enterprises |
Heitkamp Construction Co Inc |
| ITEM NO. |
ITEMS |
| Qty |
Units |
UNIT |
AMOUNT |
UNIT |
AMOUNT |
UNIT |
AMOUNT |
UNIT |
AMOUNT |
| 1 |
Mobilization & Site Preparation |
1 |
LS |
$ 37,000.00 |
$ 37,000.00 |
$26,500.00 |
$ 26,500.00 |
$49,500.00 |
$ 49,500.00 |
$30,000.00 |
$ 30,000.00 |
| 2 |
Install 8'x16' Articulated Concrete Block Sections |
3 |
EA |
$ 1,700.00 |
$ 5,100.00 |
$ 150.00 |
$ 450.00 |
$ 2,200.00 |
$ 6,600.00 |
$ 1,850.00 |
$ 5,550.00 |
| 3 |
Bank Shaping & Excavation |
2,520 |
CY |
$ 2.00 |
$ 5,040.00 |
$ 4.50 |
$ 11,340.00 |
$ 1.08 |
$ 2,721.60 |
$ 10.00 |
$ 25,200.00 |
| 4 |
Geotextile Fabric (Non-Woven) F&I |
9,340 |
SY |
$ 1.50 |
$ 14,010.00 |
$ 2.35 |
$ 21,949.00 |
$ 0.80 |
$ 7,472.00 |
$ 2.50 |
$ 23,350.00 |
| 5 |
Class C Riprap F&I |
7,050 |
TONS |
$ 50.50 |
$ 356,025.00 |
$ 48.00 |
$ 338,400.00 |
$ 14.90 |
$ 105,045.00 |
$ 58.00 |
$ 408,900.00 |
| 6 |
Traffic Control |
1 |
LS |
$ 500.00 |
$ 500.00 |
$ 500.00 |
$ 500.00 |
$ 500.00 |
$ 500.00 |
$ 6,000.00 |
$ 6,000.00 |
| |
|
TOTAL BASE BID: |
$ 417,675.00 |
$ 399,139.00 |
$ 171,838.60 |
$ 499,000.00 |
| |
|
Total FAX Mod-Add: |
|
|
|
|
| |
|
Total FAX Mod-Ded: |
|
|
|
|
| |
|
Final Base Bid: |
$417,675.00 |
$399,139.00 |
$171,838.60 |
$499,000.00 |
| |
|
|
|
|
|
|
|
|
|
|
|
| |
BID QUANTITIES |
BIDDERS |
| Lien Transportation & Construction |
Hills Materials |
Jerke & Sons Construction |
RS Halstead Corp |
| ITEM NO. |
ITEMS |
| Qty |
Units |
UNIT |
AMOUNT |
UNIT |
AMOUNT |
UNIT |
AMOUNT |
UNIT |
AMOUNT |
| 1 |
Mobilization & Site Preparation |
1 |
LS |
$125,000.00 |
$ 125,000.00 |
$19,000.00 |
$ 19,000.00 |
$38,524.18 |
$ 38,524.18 |
$41,000.00 |
$ 41,000.00 |
| 2 |
Install 8'x16' Articulated Concrete Block Sections |
3 |
EA |
$ 4,750.00 |
$ 14,250.00 |
$ 1,600.00 |
$ 4,800.00 |
$ 1,900.00 |
$ 5,700.00 |
$ 2,550.00 |
$ 7,650.00 |
| 3 |
Bank Shaping & Excavation |
2,520 |
CY |
$ 13.50 |
$ 34,020.00 |
$ 4.50 |
$ 11,340.00 |
$ 1.65 |
$ 4,158.00 |
$ 8.00 |
$ 20,160.00 |
| 4 |
Geotextile Fabric (Non-Woven) F&I |
9,340 |
SY |
$ 2.76 |
$ 25,778.40 |
$ 1.00 |
$ 9,340.00 |
$ 1.15 |
$ 10,741.00 |
$ 2.00 |
$ 18,680.00 |
| 5 |
Class C Riprap F&I |
7,050 |
TONS |
$ 70.00 |
$ 493,500.00 |
$ 47.00 |
$ 331,350.00 |
$ 50.98 |
$ 359,409.00 |
$ 53.44 |
$ 376,752.00 |
| 6 |
Traffic Control |
1 |
LS |
$ 6,500.00 |
$ 6,500.00 |
$ 500.00 |
$ 500.00 |
$ 1,000.00 |
$ 1,000.00 |
$ 2,500.00 |
$ 2,500.00 |
| |
|
TOTAL BASE BID: |
$ 699,048.40 |
$ 376,330.00 |
$ 419,532.18 |
$ 466,742.00 |
| |
|
Total FAX Mod-Add: |
|
$ 1,750.00 |
|
|
| |
|
Total FAX Mod-Ded: |
|
|
|
|
| |
|
Final Base Bid: |
$699,048.40 |
$378,080.00 |
$419,532.18 |
$466,742.00 |
| |
BID QUANTITIES |
BIDDERS |
|
| Gratech Company |
Webster Scale Inc |
Quinn Construction |
|
| ITEM NO. |
ITEMS |
| Qty |
Units |
UNIT |
AMOUNT |
UNIT |
AMOUNT |
UNIT |
AMOUNT |
| 1 |
Mobilization & Site Preparation |
1 |
LS |
$ 24,227.50 |
$ 24,227.50 |
$50,000.00 |
$ 50,000.00 |
$20,000.00 |
$ 20,000.00 |
| 2 |
Install 8'x16' Articulated Concrete Block Sections |
3 |
EA |
$ 2,640.81 |
$ 7,922.43 |
$ 3,000.00 |
$ 9,000.00 |
$ 2,500.00 |
$ 7,500.00 |
| 3 |
Bank Shaping & Excavation |
2,520 |
CY |
$ 5.06 |
$ 12,751.20 |
$ 5.00 |
$ 12,600.00 |
$ 5.00 |
$ 12,600.00 |
| 4 |
Geotextile Fabric (Non-Woven) F&I |
9,340 |
SY |
$ 2.50 |
$ 23,350.00 |
$ 1.50 |
$ 14,010.00 |
$ 1.50 |
$ 14,010.00 |
| 5 |
Class C Riprap F&I |
7,050 |
TONS |
$ 28.60 |
$ 201,630.00 |
$ 54.00 |
$ 380,700.00 |
$ 33.00 |
$ 232,650.00 |
| 6 |
Traffic Control |
1 |
LS |
$ 1,250.00 |
$ 1,250.00 |
$ 2,750.00 |
$ 2,750.00 |
$ 2,000.00 |
$ 2,000.00 |
| |
|
TOTAL BASE BID: |
$ 271,131.13 |
$ 469,060.00 |
$ 288,760.00 |
| |
|
Total FAX Mod-Add: |
|
|
|
| |
|
Total FAX Mod-Ded: |
|
|
|
| |
|
Final Base Bid: |
$271,131.13 |
$469,060.00 |
$288,760.00 |
| |
|
|
|
|
|
|